El Paso County approves tax break for affordable housing development

BY BREEANNA JENT breeanna.jent@gazette.com

El Paso County commissioners on Tuesday approved a 25year tax incentive agreement with the Colorado Springs Urban Renewal Authority to build a new housing development on the city’s southeast side, an area where county leaders said they have long sought to reduce blight and provide more affordable housing.

Cohen-esrey Development

Group expects to begin constructing the new $35 million, 137-unit affordable housing apartment complex at 1609 Zebulon Drive — near the intersection of Verde Drive and South Academy Boulevard — in late October or mid-november, its Development Director Lisa Sorensen said.

Construction on the complex, known as Lofts at 1609, will take about 19 months and should wrap up around May 2023, she said.

“This is a tremendous win for the southeast region, bringing some brand-new affordable housing units into the inventory of that region,” said El Paso County Economic Development Executive Director Crystal Latier.

The new four-story apartment complex will serve residents earning between $17,000 and $57,000 a year and will include 137 one-, twoand three-bedroom apartments that are just under 1,000 square feet on average, Sorensen said.

Rents will be 17% to 25% below market rate properties and will include utilities, she said. It will cost between $459 and $1,071 a month to rent a one-bedroom unit; between $551 and $1,268 a month for two-bedroom units; and between $636 and $1,485 for three-bedroom units, Sorensen said.

The complex will also include amenities like a fitness center, playground, dog park, dog showers and indoor bicycle storage, she said. A planned community room may also be used for community meetings, after-school tutoring and employment outreach, among other initiatives.

“We want to connect this project to the community,” Sorensen said.

More than $35 million has been secured for the project from a mix of state, county and city money, Sorensen said. The tax break approved by commissioners Tuesday will provide about $1.6 million more for the project, or about 4.5% of the project’s total financing, she said.

The additional $1.6 million in funding is essential to the project, which wouldn’t be viable without it, Sorensen said.

The tax break could cost the county an average of about $358,486 over the 25-year agreement period, El Paso County Controller Nikki Simmons said, or an average of about $14,339 a year. Simmons said she expects the final cost to the county in 2045, the last year of the agreement, to be about $20,600.

El Paso County will continue receiving just under $18,500 in base taxes on the property, and excess revenues under tax increment financing will go to the Colorado Springs Urban Renewal Authority for the project, Simmons said. Per the agreement, the authority can spend 100% of property tax increment revenues on the project.

There won’t be an impact to the county’s specific ownership taxes because there is not a metropolitan district proposed, Simmons said. Creating a metro district and its own levy would affect the county’s tax.

Commissioner Longinos Gonzalez said he would feel more comfortable allowing the authority to spend 87.5% of property tax increment revenues for the new complex instead of 100% of revenues because it would allow the county to use the funds for other services. Gonzalez ultimately voted to approve the agreement because the project was relatively small and the cost “relatively low.”

“Housing in general has become more and more of a prevailing issue for everybody,” he said. “… The fact that this one is a specific affordable housing project versus a general housing project does give me some confidence that this is a strong and worthwhile investment, because that’s what this is.”

Commissioner Cami Bremer heralded the agreement as one option local governments have to address what she called the “housing affordability and attainability crisis.”

“This is one of the tools we have to actually impact the projects that are viable in an area that really, really needs them,” she said. “I’m excited to see this.”